Article
What happens if it all goes wrong?
This is a short overview of dispute resolution within the construction
industry. It is intended as an introduction with more detailed articles,
on specific issues, being published over the following months.
When entering into a contract in the construction industry, just like
any other industry sector, you would be ill advised to sign on the
dotted line without having a lawyer review the contract on your behalf.
Many people take the view that this is an expense they can do without.
However, this is frequently a false economy, as many a dispute arises
from a failure to take legal advice in advance. Even when contracting
on the basis of a standard form, such as JCT or ICE, lawyers' advice
should be sought. This is because the individual facts of every case
vary and whilst it may be suited to one party in a certain scenario,
it may not be suited to another. Furthermore, it is uncommon for a
standard form contract to be found in a wholly standard form. The
amendments will generally run to many pages.
When contemplating contracting on the basis of a bespoke contract,
particularly if it is the other party's terms and conditions, we cannot
emphasise strongly enough the need for legal scrutiny. If the parties
do find themselves in dispute, the parties should maintain a commercial
stance and continue to talk with a view to settling their differences.
Too often we see situations deteriorating, positions becoming entrenched
and parties rushing headlong into an acrimonious dispute. Where one
or more parties is not conducting themselves in a commercial manner,
other forms of dispute resolution exist. In the construction sector,
the most common forms of dispute resolution are as follows:
= adjudication
= ADR and mediation
= arbitration
= litigation
Adjudication - Adjudication under the Housing Grants, Construction
and Regeneration Act 1996 has become the predominant means of resolving
disputes in the construction industry. Section 108 of this Act provides
parties to construction contracts with a right to refer disputes under
the contract to adjudication. It sets out certain minimum procedural
requirements which enable a party to a dispute
to refer the matter to an independent party who is then required to
make a decision within 28 days of the matter being referred. If a
construction contract does not comply with these requirements, a statutory
default scheme called the Scheme for Construction Contracts ("the
Scheme") will apply. Adjudication does not necessarily achieve
final settlement of a dispute because either of the parties has the
right to have the same dispute heard afresh in court (or where the
contract specifies arbitration, in arbitration proceedings). Nevertheless,
recent experience shows that the majority of adjudication decisions
are accepted by the parties as the final result. The legislation provides
that adjudication can be used at any time. For example, provided the
parties have a written contract (the definition of "written"
is wide), it can be used to decide contractual disputes with designers
before construction begins; it can be used to resolve contractual
disputes with and between designers, contractors and sub-contractors
both during construction as well as after completion.
Once a dispute has arisen between the parties, either party may seek
adjudication. The adjudicator is selected within a week and must decide
the dispute within a further four weeks (subject to any agreed
extension). Once the adjudicator has made a decision, the other party
must comply with it. If he does not, a court hearing to compel compliance
can usually be obtained within a matter of days.
Adjudication is thus very quick in comparison with other methods of
dispute resolution such as arbitration or litigation and it can also
be used during the currency of a contract. Adjudication can be a simple
procedure, so in many cases there is no need to involve lawyers or
other advisers. It is usually more cost effective than arbitration
or litigation.
Alternative Dispute Resolution ("ADR") - ADR covers a whole
range of consensual dispute resolution techniques from mediation through
to mini trials. Mediation is effectively a structured means of
facilitating negotiation aimed at achieving a negotiated settlement
which is acceptable to both parties. The parties are assisted in their
negotiations by a third party, a neutral mediator, who will discuss
the
issues with the parties in open or private sessions, assist the parties
to understand the strengths and weaknesses in their positions and
identify avenues for settlement which often involve issues and options
outside the immediate matters in dispute. Mediation is actively encouraged
by the courts and is ideally suited to parties who have a commercial
view and an interest in reaching a negotiated settlement,
but just need a little further assistance and encouragement to do
so.
Early Neutral Evaluation ("ENE") involves the use of a
third party neutral expert to give a non-binding opinion on technical
or legal issues which are likely to assist the parties in settling
their dispute. This
has been expanded upon to develop a system of expert determination
with the parties agreeing to be bound by the outcome. This has gained
some popularity as the dispute is decided by an industry expert and
the costs are significantly less than arbitration or litigation.
Arbitration - Most standard forms of construction contracts contain
an arbitration clause for the resolution of disputes arising under
the contract, but as a result of the Housing Grants, Construction
and Regeneration Act 1996, the initial form of dispute resolution
now tends to be adjudication.
However, arbitration still remains a common forum for resolving construction
disputes. If there is an arbitration clause in the contract, the court
will automatically stay court proceedings to allow the
parties to complete the arbitration process. Following the recent
reforms of the Technology and Construction Court ("TCC")
it remains to be seen whether arbitration will maintain its popularity
as a dispute resolution forum. The TCC has now tailored itself to better
meet the needs of the construction industry. The judges have impressive
construction expertise and it has become apparent that resolving a dispute through litigation in the TCC can be both quicker
and less costly than resorting to arbitration. There are further complications
where the dispute has an international flavour. Where the parties in dispute reside in different jurisdictions, there is
often a reluctance on behalf of each party to submit to the home courts
of the other. Furthermore, the greatly increased scope for enforcement
of arbitration awards around the world provided by the New York Convention
on Recognition and Enforcement of Foreign Arbitral Awards means arbitration
is more attractive. Enforcing an English
High Court judgment within a foreign jurisdiction can be fraught with
difficulties.
Litigation - Known previously, until 9 October 1998, as the Official
Referees Court, the TCC is one of the specialist courts of the Queen's
Bench Division. Recent years have seen a reduction in the number of
cases being heard by the TCC. This was partly due to concerns in respect
of the time taken and the costs involved. However, to a greater extent,
it was the advent of the Housing Grants, Construction and Regeneration
Act 1996 ("the Construction Act") and the adjudication procedure
it contained, which had a dramatic impact on litigation in the TCC.
The TCC is a national court whose principal venue is located in St
Dunstan's House in London. As well as London, full time judges also
sit in Birmingham, Manchester and Leeds. In addition, circuit judges
of varying levels of seniority sit part time in the TCC in other court
centres around the country and some smaller TCC disputes are dealt
with in the County Courts.
Recent reforms of the TCC have resulted in the appointment of more
judges of greater seniority and the streamlining of the rules and
procedures within the court. This resulted in publication of a revised
edition of the TCC Guide in October of last year. A principal task
for the TCC is to deal promptly and expeditiously with the litigation,
in a manner which is consistent with the policy of the Construction
Act. It does appear that earlier criticisms of the time taken to hear
matters in the TCC are now unjustified. In the recent case of Carillion
Construction Limited -v- Devonport Royal Dockyard [2005] EWHC
778 [TCC] proceedings were commenced by both parties separately
on 4 April 2005, there was a two day trial on 20 and 21 April and
judgment was given on 26 April. This may not be entirely typical but
is an example of the expeditious manner in which cases are being decided
within the TCC. The quality of the judges
within the TCC is now without question and the TCC is able to offer
speedy trial dates. The speed and costs of litigation in the TCC compare
favourably with other forms of construction dispute resolution and
litigation is now probably a more attractive proposition than arbitration.
In the next edition, we will take a more detailed look at the adjudication
process.
For further enquiries please contact Chris Whittington (view
full profile) on 01892 701222 or email chris.whittington@ts-p.co.uk.
You will require the Adobe Acrobat Reader to read PDF files, this
is free to download if you do not already have it.
Get
Adobe Reader