
Insight
On 15 November 2024, the UK’s Civil Justice Council (the CJC) concluded its review of the pre-action protocols, publishing part two of its final report. This follows the publication of the interim report in November 2021, and part one of the final report in August 2024.
In this final entry of the review, the CJC makes recommendations for reforms to the pre-action protocols. The CJC made various recommendations to specific pre-action protocols, but largely left the pre-action protocol for construction and engineering disputes alone.
The pre-action protocol for construction and engineering disputes governs parties’ conduct before the issuing of court proceedings. It does not apply where the parties refer a dispute to adjudication (as to which, see our overview here).
The aim is to encourage parties to a dispute to set out their respective cases and exchange sufficient information in order that they understand each other’s position. This, in turn, allows the parties to try to narrow the issues in dispute and try to have sensible discussions for settlement of those issues.
Its success is one of the reasons why the vast majority of construction disputes settle prior to the commencement of formal proceedings. We deal with an overview of methods of Alternative Dispute Resolution for construction disputes here.
You can access a copy of the pre-action protocol by following the link here [https://www.justice.gov.uk/courts/procedure-rules/civil/protocol/prot_ced], but for a brief summary, you can refer to the information below.
If no settlement is achieved at the pre-action meeting, or no meeting is held 14 days after the date on which it should have been, the pre-action protocol comes to an end and the claimant will often issue proceedings to commence court action.
Within certain parameters, it is open to the parties to amend these deadlines, and reasonable extensions will usually be agreed, depending on the circumstances of the dispute.
Broadly speaking, the CJC was satisfied that the pre-action protocol for construction and engineering disputes is generally working well in practice. This view is shared by most practitioners of construction disputes (particularly given its non applicability to adjudications).
The main areas of consideration by the CJC, and its conclusions, were as follows:
Whereas other pre-action protocols have been subject to recommendations for some significant changes, the CJC’s review has found the construction protocol to be in good shape with no need for any significant overhaul.
If changes are implemented based on the CJC’s current recommendations, they are unlikely to be substantial and will typically follow the advice that lawyers have been providing their clients since the introduction of this protocol, in any case.
What remains is that, if you wish to send, or have received, a letter of claim sent under the pre-action protocol for construction and engineering disputes, you should contact one of our team who will be glad to assist.