Search results for ''...


Sorry, there were no results

Get In Touch

By submitting an enquiry through 'get in touch' your data will only be used to contact you regarding your enquiry. If you would like to receive newsletters from Thomson Snell & Passmore please use the separate form below.

Newsletter Sign Up

General Private Client UpdatesGeneral Commercial UpdatesConstruction UpdatesCourt of Protection UpdatesAgriculture & Rural Affairs UpdatesCommercial Property UpdatesEmployment UpdatesDispute Resolution UpdatesCorporate & Commercial UpdatesCharities & Not for Profit UpdatesFood & Drink UpdatesEducation UpdatesTransport & Logistics UpdatesFamily Business & Owner Managed Businesses Updates

I agree to be ‘opted in’ to receive Thomson Snell & Passmore newsletters, event invitations and other publications that are related to the subject matter of this event or my industry sector. I understand that this means they will send me these communications by email

I agree

If you want to update what types of information you want to receive from us, or if you wish to stop receiving these communications, you can do so ay any time using the following link: or emailing us at .

We respect your privacy, information you submit to us will be treated in accordance with our & .

Get In Touch

By submitting an enquiry through 'get in touch' your data will only be used to contact you regarding your enquiry. If you would like to receive newsletters from Thomson Snell & Passmore please use the separate form below.

Newsletter Sign Up

General Private Client UpdatesGeneral Commercial UpdatesConstruction UpdatesCourt of Protection UpdatesAgriculture & Rural Affairs UpdatesCommercial Property UpdatesEmployment UpdatesDispute Resolution UpdatesCorporate & Commercial UpdatesCharities & Not for Profit UpdatesFood & Drink UpdatesEducation UpdatesTransport & Logistics UpdatesFamily Business & Owner Managed Businesses Updates

I agree to be ‘opted in’ to receive Thomson Snell & Passmore newsletters, event invitations and other publications that are related to the subject matter of this event or my industry sector. I understand that this means they will send me these communications by email

I agree

If you want to update what types of information you want to receive from us, or if you wish to stop receiving these communications, you can do so ay any time using the following link: or emailing us at .

We respect your privacy, information you submit to us will be treated in accordance with our & .

  • Overview

    If they have not, it can be an easy target to submit an application to the tribunal to request that the claim(s) be dismissed by the tribunal for being out of time.

    Since 2014, before a claimant can lodge a claim in an employment tribunal, they must commence the ACAS Early Conciliation (EC) process within their original limitation date.  Once the ACAS EC process has been concluded, ACAS produce an EC Certificate.

    Until the ACAS EC Certificate is provided, the three months time clock for the original limitation date is essentially paused.  However, once the ACAS EC Certificate is provided, a calculation needs to be done to discern the revised limitation date.  This calculation has been the source of headaches for employment lawyers, parties to claims and tribunals alike.  Part of this confusion arises from the two ways in which you can ‘count time’ following the ACAS EC process.
     

    Calculating time under 207B(3) 

    Counting time under 207B(3) of the Employment Rights Act 1996 states that those days between Day A (the date that the claimant commenced the ACAS EC process) and Day B (the day the ACAS EC Certificate is provided) are counted and added onto the original limitation date. 

    Example 1 

    Claimant 1 is dismissed on the 2 June.  The original limitation date to bring an unfair dismissal claim is therefore 1 September.

    Claimant 1 starts the ACAS EC process on 5 July (Day A), but the process is brought to an end on the 27 July (Day B).  There are 22 days between Day A and Day B.  The original limitation date is extended until the 23 September 2018.
     

    Calculating time under 207B(4)

    Counting time under 207B(4) means  that where the original limitation date would fall between the period of Day A and one month after Day B, then the original limitation date is extended to the end of the period instead.

    Example 2 

    Claimant 2 is dismissed on the 3 May.  The original limitation date to bring an unfair dismissal claim is therefore 2 August.

    Claimant 2 starts the ACAS EC process on 4 July (Day A) and is brought to an end on the 27 July (Day B).  Because the original limitation date (2 August) falls within the time period specified above, the limitation period would be extended to 27 August.
     

    Sequential calculations, not alternative

    But how do the two methods of calculation work together?  Very good question!  The recent case of Luton Borough Council v Haque looked at this point.

    The outcome of Haque was that the two methods of calculations are sequential, not alternative.  But fear not, we are not talking about adding months of time for claimants’ to formulate their thoughts and level claims.  No, the purpose is to always ensure that there is one month of time, roughly the length of a ‘standard’ ACAS EC process, for Claimants to present their claim(s) to tribunal.  So whichever method of calculation gives the claimant a greater length of time to lodge their claim(s) will apply. 

    Turning to the above examples, applying the other method of calculation to either would result in the a detriment to the claimant by shortening their limitation period.    

    So when does this kick in?  Well, check out Example 3 below.

    Example 3

    Claimant 3 is dismissed on the 25 April.  The original limitation date to bring an unfair dismissal claim is therefore 24 July.

    Claimant 3 starts the ACAS EC process on 29 June (Day A).  The ACAS EC process runs its course and the ACAS EC Certificate is provided on the 23 July (Day B).

    Calculating the extension of time under 207B(3) would give 24 days and so the limitation period would expire on 17 August.  Whereas calculating the extension of time under 207B(4) gives an extension until 23 August. The latter is the correct calculation.  

    If Claimant 3 had started the ACAS EC process on 25 May (Day A) and had ended on the 25 June (Day B) then clearly 207B(3) would take precedence, because it would extend the limitation period to 25 August whereas 207B(4) would only extend the period until 25 July.

    It can be difficult to get to grips with ‘counting time’ but it is an essential weapon in all of our commercial client’s arsenals.  By doing so, you equip yourselves with a potential shield to defend claims.

    If you have any concerns about active or potential claims, please do not hesitate to contact us.  

  • Related Services

    Employment Advice for Employees

    Our employment solicitors give straightforward legal advice, find proactive solutions and achieve quick results

    Employment

    We act for businesses of all shapes and sizes and in many different sectors. Our advice covers all aspects of the employment relationship, helping to settle disputes, defending employment tribunal claims and providing immigration compliance audits.

    Employment policies

    We have a wealth of experience in drafting employment policies and procedures.

Get In Touch

By submitting an enquiry through 'get in touch' your data will only be used to contact you regarding your enquiry. If you would like to receive newsletters from Thomson Snell & Passmore please use the separate form below.

Newsletter Sign Up

General Private Client UpdatesGeneral Commercial UpdatesConstruction UpdatesCourt of Protection UpdatesAgriculture & Rural Affairs UpdatesCommercial Property UpdatesEmployment UpdatesDispute Resolution UpdatesCorporate & Commercial UpdatesCharities & Not for Profit UpdatesFood & Drink UpdatesEducation UpdatesTransport & Logistics UpdatesFamily Business & Owner Managed Businesses Updates

I agree to be ‘opted in’ to receive Thomson Snell & Passmore newsletters, event invitations and other publications that are related to the subject matter of this event or my industry sector. I understand that this means they will send me these communications by email

I agree

If you want to update what types of information you want to receive from us, or if you wish to stop receiving these communications, you can do so ay any time using the following link: or emailing us at .

We respect your privacy, information you submit to us will be treated in accordance with our & .

^
Jargon Buster